OnPath Energy completes financial close at co-located South Yorkshire solar energy and battery storage site
OnPath Energy has secured financial close on Common Farm Solar Park in South Yorkshire, marking its first project to combine solar generation with battery storage on the same site.


The developer is building the 49 MW solar scheme and 50MW two-hour battery energy storage system close to the Todwick Road Industrial Estate in Dinnington, to the east of Sheffield. The project is expected to generate enough electricity for up to 18,800 family homes a year.
A subsidy free, long-term route to market contract has been agreed with a global technology company for the solar asset, alongside a third-party optimisation agreement for the battery storage element. NatWest has provided project financing for the combined asset, including a term loan and other ancillary facilities covering the construction and operational phases.


Construction is due to be completed by mid-2027.
Local consultation is continuing on how an annual community benefits package of around £50,000 should be used. Over the lifetime of the scheme, that could total around £2,000,000 and be directed towards local community and environmental priorities.
AECOM is acting as lead consultant on the project, while specialist engineering contractor Grupotec is handling design, engineering, procurement and construction. Once electricity generation begins, Grupotec will also carry out operational maintenance and management work.
Oliver Hartley, finance director at OnPath Energy, said: “While there are currently few co-located sites across the UK, especially at this scale, it makes technical and operational sense to place solar and battery technologies in the same location and allows for efficient use to be made of the available grid connections.
“Reaching financial close on our first co-located solar and battery site demonstrates the confidence that all parties have in the project’s commercial potential, the effectiveness of the different technologies we’re utilising and the strength of our relationships with our lenders, advisors and suppliers.
“Work is progressing well on the Common Farm Solar and BESS Park, which we’ve been able to deliver thanks in part to our RCF, enabling us to deliver our project plans with maximum efficiency.
“Delivering this project will further enhance OnPath Energy’s contribution towards reducing the UK's dependence on imported fossil fuels and strengthening its energy security while also delivering a wide range of direct environmental, economic and community benefits to the local area.”