YORKSHIRE RAIL CHAOS: Industry believed it could deliver new timetables 'until last moment'

The rail industry believed 'until the last moment' that it could successfully introduce the new timetables that have led to major disruption, Transport Secretary Chris Grayling said.
Transport Secretary Chris Grayling.Transport Secretary Chris Grayling.
Transport Secretary Chris Grayling.

He accepted people would find that 'hard to understand', amid mass cancellations and delays on Northern services across Yorkshire and GTR services elsewhere in the country.

In a statement in the Commons, Mr Grayling revealed that GTR 'assured me personally that they were ready' just three weeks before services were rescheduled on May 20.

Hide Ad
Hide Ad

"Clearly this was wrong and it is totally unacceptable," he said.

"The rail industry has collectively failed to deliver for the passengers it serves.

"It's right that the industry has apologised for the situation that we are currently in and that we learn the lessons for the future."

Mr Grayling faced repeated calls from Labour MPs, who branded him 'utterly pointless'.

Hide Ad
Hide Ad

Conservative MPs focused their ire on the rail industry rather than their party colleague.

Mr Grayling reiterated previous comments about Government-owned Network Rail being 'very late' to finalise new timetables and not completing infrastructure upgrades in time on Northern routes.

But he also attacked the private train operators, saying that Northern and GTR were 'not sufficiently prepared'.

GTR did not have enough drivers with the route knowledge required to operate the new timetable and 'neither Northern nor GTR had a clear fall-back plan', he told the Commons.

Hide Ad
Hide Ad

The process of introducing the new timetable was overseen for the last two years by an Industry Readiness Board, made up of Network Rail, the Office of Rail and Road and the train operators, and an Independent Assurance Panel.

"Both of these groups have told me that they had been given no information to suggest that the new timetable should not be implemented as planned - albeit with some likely early issues as the timetable bedded down," Mr Grayling said.

"It should have been clear to them that some key parties were not ready. They did not raise this risk."

Mr Grayling announced that the Department for Transport would assess whether GTR and Northern 'met their contractual obligations in the planning and delivery of this timetable change'.

Hide Ad
Hide Ad

In relation to GTR, this would include its 'eligibility to hold a franchise bidding passport', which is a requirement to bid for future rail contracts.

The ORR will also carry out a full inquiry.

A "compensation scheme" will be introduced for passengers on affected routes which will be funded by the industry to ensure "regular rail customers receive appropriate redress", Mr Grayling said.

Northern and GTR launched interim timetables on Monday, removing 165 and 230 daily services respectively. This is around 6 per cent of all services.

The reduced timetables failed to stop Monday becoming the start of a third week of rail chaos with the number of trains either cancelled or more than 30 minutes late for Northern and GTR reaching 133 (6 per cent) and 171 (7 per cent) respectively by 7pm, according to the trains.im website.

Hide Ad
Hide Ad

The timing of all GTR and most Northern trains was changed on May 20 with the launch of new services and capacity.

Even before the new timetables, Northern services suffered frequent delays and cancellations.

New Network Rail punctuality data shows that between April 29 and May 26, more than one in three (35 per cent) trains on the operator's Lancashire and Cumbria routes were delayed by at least five minutes.

This is the most since Arriva Rail North took over the franchise in April 2016.