Old well found beneath Sheffield tram track as blue route travel disruption continues

Oliver Coppard has revealed the reasons for further tram disruption today

An old well believed to date back to Sheffield’s coal-mining past has been discovered beneath the tram track at Birley Lane.

The discovery has revealed the cause of an infrastructure problem which has left blue route services suspended between Gleadless and Halfway.

South Yorkshire Mayor Oliver Coppard in his office in Sheffield.placeholder image
South Yorkshire Mayor Oliver Coppard in his office in Sheffield.

Mayor of South Yorkshire, Oliver Coppard, said the well appears to have been underneath the track since the section of the network was built in the early 1990s.

It is understood the track was laid directly over the well, which does not appear to have been recorded in the historic records currently available.

He said: “Yesterday morning, my team spotted an issue with the tram track in the area. They then suspended tram services whilst safety checks were undertaken and have now uncovered what appears to be an old well beneath the line, which likely dates back to when the area was used for coal mining.

“It looks like when this section of the Supertram network was built back in the early 1990s, the track was laid directly over it. As far as we can tell, it wasn’t documented in the records we have today, so it’s a bit of a surprise…

Coppard said that work is now focused on making the area safe and carrying out a proper repair - though he warned this would not be a quick fix.

“As you’d expect, the most important thing now is making the area safe and fixing it properly.

“Unfortunately, that won’t be a quick repair, but the safety of passengers and staff has to come first. We’re now also checking historic records for other potential wells in the area,” he said.

“I'm sorry for the disruption. I know how much people rely on the tram network every day,” he said.

The latest update comes after Supertram first reported an issue near Birley Lane, in the Frecheville area of Sheffield, shortly after 8am on Sunday, August 23.

More than 24 hours later, there were still no blue route services operating between Gleadless and Halfway in either direction.

At the time, passengers were told services were being disrupted because of an “ongoing issue” with the infrastructure.

This disruption has added to existing problems on Sheffield’s tram network, which is already affected by planned engineering works in the city centre.

For passengers travelling the full Blue Route from Halfway to Malin Bridge, the disruption has meant a journey that would normally be completed on one tram now requires two replacement buses and two separate tram services.

Coppard has provided some positive news though. In his statement he shared that work to replace the Delta Junction at Park Square is now expected to finish on Thursday, four days earlier than planned.

He said: “The good news is that work to replace the Delta Junction at Park Square is on track to finish this Thursday, four days earlier than planned.

Most services are then expected to return to their usual timetables, running through Sheffield city centre to Meadowhall, Rotherham Parkgate, Middlewood, Malin Bridge and Herdings Park.

However, Blue Route trams will run to Herdings Park instead of Halfway.

The replacement bus service from Gleadless Townend to Halfway will also continue to operate.