Replacement buses serving an area of Sheffield that has been completely cut off from the tram network after the discovery of a historic mineshaft under the tracks are costing more than £6,000 a day.

South Yorkshire Mayoral Combined Authority (SYMCA), which manages the city’s trams, has revealed the local authority is paying £6,267.74 per day for replacement bus services following the discovery of the huge hole at Birley.

Tram hole at Birley Lane.placeholder image
Tram hole at Birley Lane.

The costs cover the BL1 tram replacement bus service, which was commissioned after a large hole was discovered underneath tram tracks near to Birley Lane in August this year.

The blue Supertram route now only operates between Malin Bridge and Herdings Parks.

SYMCA said that a “competitive tender exercise” to secure the replacement bus service, which has been awarded to First.

The contract is set to run until December 31, with an estimated total cost of £256,977.34.

However, documents show that SYMCA could extend the contract to March 31, 2027.

A document published by SYMCA adds: “Temporary amended service levels are expected during the Christmas and New Year period to reflect reduced customer demand and operational requirements.

“The final value payable may therefore vary slightly from the estimated contract value where reduced service levels are agreed and delivered.”

It is believed that the hole under the tracks could date back more than 150 years, with survey maps from the 19th century showing a ‘shaft’ in the area.

Businesses at the Crystal Peaks shopping centre have complained of decreased trade due to the ongoing tram disruptions, with South Yorkshire Mayor Oliver Coppard recently hosting discussions about what assistance could be provided.

Mayor Coppard has said there is not a simple fix for the hole and that it is unlikely to be resolved this year.

South Yorkshire Mayor Oliver Coppardplaceholder image
South Yorkshire Mayor Oliver Coppard | Iconic Media

During his monthly Q&A with The Star, the mayor said his team were working as “quickly as humanly possible” to find a solution, adding: “You can't just shovel concrete down there or rubble because unless and until you know what's down there and where it connects you could contaminate the water base the the water system by putting in concrete and it leaks into, seeps into people's water supply.

“We absolutely don't want that.”

A SYMCA spokesperson said: “Our priority is to get Birley Lane safely re-opened as soon as we can, but the reality is that won’t be this side of Christmas.

“We’re still investigating exactly what’s beneath the track to confirm the details of what work will be needed to put it right and provide a long-lasting fix that is safe and reliable for decades to come.

“To help make sure passengers can complete their journeys, we carried out a competitive tender exercise for a bus replacement service. Following evaluation of the submitted tenders, First was identified as the successful bidder.

“The initial contract takes us up to the end of December. As we have previously said the work will run into 2027 and so we have also agreed contingency funding to run the bus replacement service into next year as required.

“We have listened to feedback from passengers and have made various timetable amends over recent weeks to help improve performance on the replacement bus service and will continue to monitor its performance.

“Once work on the underground investigations has been completed, we will be able to confirm an expected completion date for the works to bring the Blue Route tram line back into operation as quickly and safely as possible.”