Contractors issue statement over six-week closure of A57 Manchester Road in Sheffield and 24-mile diversion
Contractors have issued a statement after concerns were raised over the six-week closure of a major road into Sheffield.
Sheffield MP Olivia Blake said she had “heard extensively” from residents about the planned closure of the A57 Manchester Road between Onksley Lane and Wyming Brook Drive, near Rivelin Dams.
She had written to Amey, the council’s roads maintenance contractor until 2039, and received a response setting out the organisation’s thinking.
Last week, Councillor Ruth Milsom asked whether full closure could be reduced or avoided.


Amey has a £2bn contract to resurface and maintain roads and pick up litter in Sheffield.
It has warned residents to expect ‘major disruption’ when the A57 closes completely from April 20 until June 2 for landslip repairs.


One week before the full closure, from April 13, and for five weeks after, until July 10, one lane will be open, controlled by temporary traffic lights.
A 24-mile diversion has been suggested - via the city centre, Ecclesall Road, Ringinglow Road, Hathersage and Bamford.
The response to Ms Blake states Amey “fully understands” and “acknowledges” people’s concerns, and is “sorry” for the inconvenience and “regrets” it is necessary. It is also a “last resort.”
But the closure is essential to safely reconstruct a retaining wall.
And “due to the narrow width of the carriageway and the scale of the excavation required, it is not possible to complete the reconstruction safely under traffic‑light control or while maintaining two‑way traffic.”


“Rest assured that, we are committed to completing the works as quickly as practicably possible and to keeping disruption to a minimum.”