Amey, who carrying out highway improvements across Sheffield as part of a £2.2 billion contract, returned to Knowle Lane, Ecclesall to fully resurface the road.
Sheffield Council said Knowle Lane was one of a small number of streets where remedial work was required after resurfacing, in this case due to 'soft underlying surface layers'.
It claimed these represented a fraction of the more than 500 miles of road already resurfaced under its Streets Ahead programme, and said its contractor Amey would foot the bill for repairs.
Most Popular
-
1
Chesterfield Road Sheffield: Man who spent 12 hours on roof is sentenced in court for affray and harassment
-
2
The Long Blondes: Leadmill cancel gig after allegations surface against band creator Dorian Cox
-
3
Chapeltown Sheffield rape investigation: 16-year-old arrested over assault of girl, 13, is bailed
-
4
EuroMillions: Mystery winner from South Yorkshire has won £79,242.50 on The National Lottery
-
5
Graves Park Sheffield: Council to give Rose Park Cafe operators 'opportunity' to run temporary stall
Nick Hetherington, network account manager for Streets Ahead, said they expected to finish the works in around two weeks.
He said the work would be carried out in two stages and involve road closures. The first section to be completed will be between Ecclesall Road South and Haugh Lane.
The Haugh Lane to Ringinglow Road section will be done after Easter. No work will take place over the Easter weekend.
Mr Hetherington said: "We’d like to apologise to local people for the disruption our work in Knowle Lane might cause them. Unfortunately, since being re-surfaced the original underlying surface layers have unexpectedly deteriorated and the road requires total reconstruction.
“We’ll be re-building the failed substructure with traditional compacted hardcore which should provide a strong base for years to come.
“Given the scale of our work in upgrading 65 per cent of the city’s roads in just five years, instances like this was are mercifully quite unusual, but we appreciate they are very inconvenient and will do our best to complete it as efficiently as we can. Please bear with us.”