Pictures taken of work which is going on behind giant boards shows how terraces have now taken shape at Castlegate, as work continues to create a £25m park on the site.
The project is due to be completed and opened next year.
Pictures also show a pathway taking shape, as well as the section where the River Sheaf can now be seen for the first time in over100 years in that location.
Originally expected to be completed in February 2026 and supposed to cost £20 million, the Castlegate Park development is now not due to be completed until the end of 2026, because bosses changed the original plans to better display and preserve the historic remains found by archaeologists on the Sheffield Castle site.
As well as delaying completion, the move also contributed to a rise in the cost of the project by around £5 million according to Sheffield Council documents.
Take a look at the 10 pictures below to see how the site is now taking shape.

9. Progress
How work is progressing behind the barriers at what is to be a park at Castlegate, Sheffield. Photo: Iconic Media | Iconic Media Photo: Iconic Media

10. Castlegate River Sheaf
This picture shows how the Sheffield Castlegate site will appear near the River Sheaf when work is completed next year, Photo: Sheffield Council | Sheffield Council Photo: Sheffield Council