A decision not to repair a steep set of steps in Wincobank, Sheffield has been criticised as short-sighted.

Coun Glynis Chapman spoke out during a meeting of Sheffield City Council’s finance and performance policy committee yesterday (October 21). A report to the committee said that plans to replace the timber steps on a footpath linking Barkby Road and Fife Street with metal ones have been dropped.

The report said that the steep set of steps “require significant ongoing maintenance due to high levels of use and vandalism”. It added: “The overall aim of this project was to reduce the ongoing maintenance costs and prevent possible insurance claims against the council due to the current condition of the steps.”

A Google Maps image of a public footpath leading from Barkby Road to Fife Street in Wincobank, Sheffieldplaceholder image
A Google Maps image of a public footpath leading from Barkby Road to Fife Street in Wincobank, Sheffield

The explanation for the change of plan was that the metal steps would cost too much and the priority for the work has reduced because there has been no recent damage.

The £82,000 budget is now planned to be spent on other repairs to rights of way in the city.

Coun Chapman said: “If these aren’t safe, why aren’t we doing it? Why is this being taken out of the programme?

“It’s written down here that we were worried that we might get possible insurance claims because they’re not safe and we’ve taken them out of the budget and, lo and behold, in a few months’ time we’ve got an insurance claim and it’s going to cost us twice as much to to do them, so I don’t know why they’ve been taken out of the budget and not being repaired.

“They’re not safe, they want repairing.”