Major road-widening to speed up buses on busy Sheffield street nears completion

A major road-widening project designed to speed up bus journeys in Sheffield is nearing completion.

Work to create a second inbound lane on Chesterfield Road, in Heeley, began last year and is due to be completed in June.

Work to widen Chesterfield Road is due to be completed in Juneplaceholder image
Work to widen Chesterfield Road is due to be completed in June

Sheffield Council said the scheme is running to schedule, other than a small delay caused by the recent heavy snow.

placeholder image
Read More
Bus journey times shortened by as much as a quarter in Sheffield through £18 mil...

BT Openreach is now on site laying cables and once its work is done, the project is expected to take another eight weeks to complete.

The extra lane created by pushing back the retaining wall would be reserved for buses at peak hours but available for all vehicles at other times.

The Chesterfield Road widening project was approved following complaints from bus passengers about the poor reliability of services.

The work was funded using a central government grant to the Sheffield Bus Partnership, comprising of First Group, Stagecoach, Sheffield Community Transport, South Yorkshire Passenger Transport Executive and Sheffield Council.